Agnes Varis Campus Center Construction Timeline

Please note that during construction students, faculty, and staff will not be allowed into the construction fence without notifying the Site Superintendent. Hard hats will be mandatory.

Schedule provides estimated milestones. Time may vary as job progresses.

Agnes Varis Campus Center
Selected Construction Milestones

Task
Start
Finish
Abatement
July 9, 2007
July 27, 2007
Selective demolition – interior and exterior
July 30, 2007
September 28, 2007
Masonry – elevator shaft, chimney, clean and repoint
September 3, 2007
December 7, 2007
Glass and Window Glazing – prep and installation
September 17, 2007
January 4, 2008
Plumbing

October 1, 2007

March 21, 2008
Roofing

November 19, 2007
January 25, 2008
Elevator – Installation
November 26, 2007
January 31, 2008
HVAC
November 26, 2007
April 4, 2008
Finish Carpentry
January 1, 2008
March 10, 2008
Flooring
January 1, 2008
April 25, 2008
Painting/Wall Covering
January 22, 2008
April 11, 2008
Kitchen Equipment
April 11, 2008
May 1, 2008
Final Inspections
April 28, 2008
May 16, 2008