Date |
Goal |
July 11, 2007 |
Site work begins |
August 6, 2007 |
Foundation work begins |
August 28, 2007 |
Metal building erection begins |
August 30, 2007 |
Rough site work completed; final grading and landscaping begin |
September 25, 2007 |
Exterior of building, including roofing and siding, complete |
September 26, 2007 |
Interior framing and finishes begin |
November 29, 2007 |
Substantial completion; punch list work begins |
December 13, 2007 |